Bypass is delayed still further and cost rises

Bypass is delayed still further and cost rises
 

0 Have your say The long awaited Broughton bypass has been delayed by a further five months and is expected to cost an extra £3m.
Due to have been completed by March 2017, the scheduled completion date for the bypass is now August next year.
Lancashire County Council says delays in construction have been caused by complications related to ground conditions, which LCC Director of Development and Corporate Services Eddie Sutton described as “more challenging than had been indicated by the initial survey”.
He said this had impacted on the work on Brooklands Bridge at the southern end of the... read more

 
3 October 2016 in Regional North West , Views: 29